Nigeria SHELL Security Enhancement Project System Integration Works
- DAS-Based Intruder Detection System:
⚬ Commissioning of the DAS-based intruder detection system to fortify perimeter security.
⚬ Integration with existing security infrastructure for a unified approach. - CCTV System:
⚬ Commissioning of the CCTV system to enhance surveillance capabilities.
⚬ Integration with other security systems for synchronized monitoring and response. - Equipment Radar System:
⚬ Commissioning of the radar system to bolster threat detection capabilities.
⚬ Integration with the overall security framework for real-time situational awareness.
———-
TEKFEN – Rectification of CCTV Camera Mounting Systems and Pedestrian Door Installation at BVS Stations
- Revitalization of camera pedestals and optimization of the mounting system.
- Executed tasks such as de-energization of CCTV cameras at BVS stations, de-installation of fixed cameras, installation of new mounting arms, and re-energization of CCTV junction boxes as per TANAP requirements.
- Commissioning and OTDR tests to guarantee integrity.
- Installation of FIDS/BIDS FO Cable compatible with the route of new pedestrian doors for improved security.
———-
ABB – TANAP PAGA & PAWS Maintenance Services
- Demonstrated commitment to TANAP’s operational reliability through routine maintenance services for PAGA (Public Address & General Alarm) and PAWS (Pipeline Audio Warning System).
- Included network modernization for online PAWS units across 56 unmanned stations.
- Provided hardware and software clarifications for PAGA detection and replaced faulty equipment, alongside software updates.
———-
TANAP – PAWS System Site Rectification Works
- Ongoing initiative focused on systematic site acceptance tests, ad-hoc system failure classification and rectification, fault finding, and resolution encompassing both hardware and software components.
- Planned modernization efforts aimed at elevating the overall efficiency of the PAWS system.
———-
PLC & IO Cards Upgrade at BTC/SCP Pipeline Block Valve Stations – GEORGIA/AZERBAIJAN
- Replacement of obsolete PLCs and I/O modules.
- Upgrade of power supplies.
- Installation, wiring and cold/hot loop checking.
- Configuration of PLC software and communication protocols.
- Testing and commissioning of the new system.
- Documentation update and compliance with BP standards.